schedule-forecaster

schedule-forecaster is a skill for Claude Code, Codex from datadrivenconstruction/DDC_Skills_for_AI_Agents_in_Construction. It costs 28 tokens per session (3,501 once invoked), scanned A, original, MIT.

A machine-learning workflow for forecasting when construction projects will finish. It uses current progress, past project patterns, weather, resources, and project details to estimate delays and completion dates.

In plain words
What is it for?
Use it to forecast completion dates, identify likely delays, plan staffing, update clients, and manage schedule risks.
Why use it?
It gives teams an earlier view of possible schedule problems than relying only on the original plan or a manual estimate.

Skill for Claude CodeCodex

Which agent this was written for is unclear — built for openclaw. Also seen: built for openclaw.

Good fit Use it to forecast completion dates, identify likely delays, plan staffing, update clients, and manage schedule risks.

Compare 6 skills from other repositories ↓
Install with agentmods
npx agentmods add skills/datadrivenconstruction/ddc_skills_for_ai_agents_in_construction/schedule-forecaster
Install

Getting it into your agent

One page per mod, every tool's command on it. A separate URL per tool would split the same page into five that compete with each other.

Any agent
npx skills add datadrivenconstruction/DDC_Skills_for_AI_Agents_in_Construction --skill schedule-forecaster
Clone the repo
git clone --depth 1 https://github.com/datadrivenconstruction/DDC_Skills_for_AI_Agents_in_Construction

Made for: Claude Code, Codex.

Wrote this? Show the measurements

A badge with what this costs and how it scanned, read live from this page, so it follows the numbers instead of freezing them. Markdown for a README, HTML for a documentation site or a project page.

agentmods badge for schedule-forecaster

README.md
[![agentmods](https://agentmods.dev/badge/skills/datadrivenconstruction/ddc_skills_for_ai_agents_in_construction/schedule-forecaster/github.svg)](https://agentmods.dev/skills/datadrivenconstruction/ddc_skills_for_ai_agents_in_construction/schedule-forecaster)
Your own site
<a href="https://agentmods.dev/skills/datadrivenconstruction/ddc_skills_for_ai_agents_in_construction/schedule-forecaster"><img src="https://agentmods.dev/badge/skills/datadrivenconstruction/ddc_skills_for_ai_agents_in_construction/schedule-forecaster/github.svg" alt="Measured on agentmods" height="20"></a>

Or the 80×15 button, for a site that already has a row of RSS and ATOM ones. Only the verdict fits; the numbers stay here.

agentmods 80×15 button for schedule-forecaster

Your own site · 80×15
<a href="https://agentmods.dev/skills/datadrivenconstruction/ddc_skills_for_ai_agents_in_construction/schedule-forecaster"><img src="https://agentmods.dev/badge/skills/datadrivenconstruction/ddc_skills_for_ai_agents_in_construction/schedule-forecaster.svg" alt="Reviewed on agentmods" width="80" height="20"></a>
Per session 28 Skills are progressive disclosure: only the name and description are preloaded; the body loads when the skill is used.
When invoked 3,501 The whole file, excluding the scripts and references it only reads on demand.
Security scan A 0 findings. A grade says what 26 rules found in the file — not that it is safe. Third-party audits
  • NVIDIA SkillSpector pass 7 Sept 2026
How audits are shown
Origin original No closer match found in the catalogue.
Token cost

What it costs to keep this loaded

Counted locally with the o200k_base tokenizer, which is exact for GPT models; Claude uses its own tokenizer and its counts differ. Treat this as one consistent yardstick across the catalogue rather than a bill. Prices are per million input tokens.

ModelPer sessionOnce invoked
Fable 5.1 $0.00028 $0.03501
Opus 5 $0.00014 $0.01750
Sonnet 5 $0.00006 $0.00700
Haiku 4.5 $0.00003 $0.00350

Measured 8d ago against content hash 4831a1b4f911, method: parsed. Prices are Anthropic first-party input rates as of 2026-09-11, from the pricing page.

Security

Grade A, and why

schedule-forecaster scanned grade A with 0 findings against 26 rules in 11 categories — prompt injection, anti-refusal, data exfiltration, privilege escalation, supply chain, agent snooping, system-prompt leakage, SSRF and excessive agency — measured 8d ago.

A static scan of the body, not an audit. Every finding is printed with the line that produced it so you can judge whether it matters here. A mod is markdown that instructs an agent; that is exactly why what it instructs is worth reading.

Nothing flagged

None of the 26 patterns this scan looks for appear in this file: no shell pipes, no recursive deletes, no credential paths, no hidden text, no instruction-override or anti-refusal phrasing, no agent-config snooping. That is not a guarantee, it is the absence of the things that are checkable.

Origin

Copies of this mod

1 near-identical copy found in the catalogue:

2_DDC_Book/4.5-ML-Cost-Prediction/schedule-forecaster/SKILL.md · 436 lines

How it starts

The opening of the file, as written. The whole thing — 436 lines — stays where its author put it; the contents beside it link to each section on GitHub.

Schedule Forecaster for Construction

Overview

Predict project completion dates using machine learning models trained on historical data. Forecast delays based on current progress, weather patterns, resource availability, and project characteristics.

Business Case

Accurate schedule forecasting enables:

  • Early Warning: Identify potential delays before they impact milestones
  • Resource Planning: Adjust staffing based on predicted needs
  • Client Communication: Provide reliable completion estimates
  • Risk Management: Proactively address schedule risks

Technical Implementation

from dataclasses import dataclass, field
from typing import List, Dict, Any, Optional, Tuple
import pandas as pd
import numpy as np
from datetime import datetime, timedelta
from sklearn.ensemble import GradientBoostingRegressor, RandomForestRegressor
from sklearn.preprocessing import StandardScaler
from sklearn.model_selection import train_test_split, TimeSeriesSplit
from sklearn.metrics import mean_absolute_error, mean_squared_error
import warnings
warnings.filterwarnings('ignore')

@dataclass
class ScheduleForecast:
    project_id: str
    forecast_date: datetime
    predicted_completion: datetime
    confidence_interval: Tuple[datetime, datetime]
    delay_probability: float
    delay_days: int
    key_risk_factors: List[str]
    recommended_actions: List[str]

@dataclass
class ProgressSnapshot:
    date: datetime
    planned_progress: float
    actual_progress: float
    earned_value: float
    planned_value: float
    spi: float  # Schedule Performance Index
    cpi: float  # Cost Performance Index

class ConstructionScheduleForecaster:
    """ML-based schedule forecasting for construction projects."""

    def __init__(self):
        self.models: Dict[str, Any] = {}
        self.scalers: Dict[str, StandardScaler] = {}
        self.feature_columns: List[str] = []
        self.is_trained = False

    def prepare_training_data(self, historical_projects: pd.DataFrame) -> Tuple[pd.DataFrame, pd.Series]:
        """Prepare features from historical project data."""

        df = historical_projects.copy()

        # Calculate target: actual delay in days
        df['planned_duration'] = (pd.to_datetime(df['planned_end']) - pd.to_datetime(df['planned_start'])).dt.days
        df['actual_duration'] = (pd.to_datetime(df['actual_end']) - pd.to_datetime(df['actual_start'])).dt.days
        df['delay_days'] = df['actual_duration'] - df['planned_duration']

        # Feature engineering
        features = pd.DataFrame()

        # Project characteristics
        if 'project_type' in df.columns:
            features = pd.concat([features, pd.get_dummies(df['project_type'], prefix='type')], axis=1)

        if 'gross_area' in df.columns:
            features['gross_area'] = df['gross_area']
            features['log_area'] = np.log1p(df['gross_area'])

        if 'contract_value' in df.columns:
            features['contract_value'] = df['contract_value']
            features['value_per_sf'] = df['contract_value'] / df['gross_area'].replace(0, 1)

        if 'planned_duration' in df.columns:
            features['planned_duration'] = df['planned_duration']

        # Complexity indicators
        if 'num_subcontractors' in df.columns:
            features['num_subcontractors'] = df['num_subcontractors']

        if 'num_change_orders' in df.columns:
            features['num_change_orders'] = df['num_change_orders']

        # Historical performance
        if 'contractor_avg_delay' in df.columns:
            features['contractor_avg_delay'] = df['contractor_avg_delay']

        # Seasonal factors
        if 'planned_start' in df.columns:
            start_dates = pd.to_datetime(df['planned_start'])
            features['start_month'] = start_dates.dt.month
            features['start_quarter'] = start_dates.dt.quarter
            features['winter_start'] = ((start_dates.dt.month >= 11) | (start_dates.dt.month <= 2)).astype(int)

        # Location factors
        if 'location_factor' in df.columns:
            features['location_factor'] = df['location_factor']

        self.feature_columns = features.columns.tolist()

        return features.fillna(0), df['delay_days']

    def train_delay_model(self, historical_projects: pd.DataFrame) -> Dict[str, float]:
        """Train model to predict schedule delays."""

        X, y = self.prepare_training_data(historical_projects)

        # Split data
        X_train, X_test, y_train, y_test = train_test_split(X, y, test_size=0.2, random_state=42)

        # Scale features
        scaler = StandardScaler()
        X_train_scaled = scaler.fit_transform(X_train)
        X_test_scaled = scaler.transform(X_test)

        # Train model
        model = GradientBoostingRegressor(
            n_estimators=100,
            max_depth=5,
            learning_rate=0.1,
            random_state=42
        )
        model.fit(X_train_scaled, y_train)

        # Evaluate
        y_pred = model.predict(X_test_scaled)
        mae = mean_absolute_error(y_test, y_pred)
        rmse = np.sqrt(mean_squared_error(y_test, y_pred))

        # Store model
        self.models['delay'] = model
        self.scalers['delay'] = scaler
        self.is_trained = True

        # Feature importance
        importance = dict(zip(self.feature_columns, model.feature_importances_))

        return {
            'mae': mae,
            'rmse': rmse,
            'training_samples': len(X_train),
            'feature_importance': importance
        }

    def train_progress_model(self, progress_data: pd.DataFrame) -> Dict[str, float]:
        """Train model to predict progress based on current trajectory."""

        df = progress_data.copy()

        # Features: current progress, SPI, historical trend
        features = []
        targets = []

        for project_id in df['project_id'].unique():
            project_data = df[df['project_id'] == project_id].sort_values('date')

            for i in range(len(project_data) - 1):
                current = project_data.iloc[i]
                final = project_data.iloc[-1]

                feature = {
                    'current_progress': current['actual_progress'],
                    'planned_progress': current['planned_progress'],
                    'progress_variance': current['actual_progress'] - current['planned_progress'],
                    'spi': current.get('spi', 1.0),
                    'cpi': current.get('cpi', 1.0),
                    'days_elapsed': i,
                    'days_remaining_planned': len(project_data) - i - 1,
                }
                features.append(feature)
                targets.append(final['actual_progress'] - current['actual_progress'])

        X = pd.DataFrame(features)
        y = pd.Series(targets)

        X_train, X_test, y_train, y_test = train_test_split(X, y, test_size=0.2, random_state=42)

        scaler = StandardScaler()
        X_train_scaled = scaler.fit_transform(X_train)
        X_test_scaled = scaler.transform(X_test)

        model = RandomForestRegressor(n_estimators=100, max_depth=10, random_state=42)
        model.fit(X_train_scaled, y_train)

        y_pred = model.predict(X_test_scaled)
        mae = mean_absolute_error(y_test, y_pred)

        self.models['progress'] = model
        self.scalers['progress'] = scaler

        return {'mae': mae, 'training_samples': len(X_train)}

    def forecast_completion(self, project_data: Dict,
                            current_progress: float,
                            current_date: datetime) -> ScheduleForecast:
        """Forecast project completion date."""

        if not self.is_trained:
            raise ValueError("Model not trained. Call train_delay_model first.")

        # Prepare features
        features = pd.DataFrame([project_data])[self.feature_columns].fillna(0)
        features_scaled = self.scalers['delay'].transform(features)

        # Predict delay
        predicted_delay = self.models['delay'].predict(features_scaled)[0]

        # Get prediction interval (using model variance)
        tree_predictions = np.array([
            tree.predict(features_scaled)[0]
            for tree in self.models['delay'].estimators_
        ])
        delay_std = np.std(tree_predictions)

        # Calculate dates
        planned_end = pd.to_datetime(project_data.get('planned_end'))
        predicted_completion = planned_end + timedelta(days=int(predicted_delay))

        confidence_low = planned_end + timedelta(days=int(predicted_delay - 1.96 * delay_std))
        confidence_high = planned_end + timedelta(days=int(predicted_delay + 1.96 * delay_std))

        # Calculate delay probability
        delay_probability = 1 / (1 + np.exp(-predicted_delay / 30))  # Sigmoid transform

        # Identify risk factors
        risk_factors = self._identify_risk_factors(project_data, features_scaled)

        # Generate recommendations
        recommendations = self._generate_recommendations(
            predicted_delay, current_progress, project_data
        )

        return ScheduleForecast(
            project_id=project_data.get('project_id', 'Unknown'),
            forecast_date=current_date,
            predicted_completion=predicted_completion,
            confidence_interval=(confidence_low, confidence_high),
            delay_probability=delay_probability,
            delay_days=int(predicted_delay),
            key_risk_factors=risk_factors,
            recommended_actions=recommendations
        )

    def _identify_risk_factors(self, project_data: Dict, features_scaled: np.ndarray) -> List[str]:
        """Identify key risk factors for the project."""
        risk_factors = []

        importance = dict(zip(self.feature_columns, self.models['delay'].feature_importances_))
        top_features = sorted(importance.items(), key=lambda x: -x[1])[:5]

        for feat, imp in top_features:
            if imp > 0.1:
                value = project_data.get(feat)
                if value:
                    risk_factors.append(f"{feat}: {value} (impact: {imp:.1%})")

        # Add context-specific risks
        if project_data.get('num_change_orders', 0) > 10:
            risk_factors.append("High number of change orders")

        if project_data.get('winter_start'):
            risk_factors.append("Winter start increases weather risk")

        return risk_factors[:5]

    def _generate_recommendations(self, predicted_delay: float,
                                   current_progress: float,
                                   project_data: Dict) -> List[str]:
        """Generate actionable recommendations."""
        recommendations = []

        if predicted_delay > 30:
            recommendations.append("Consider schedule compression techniques (crashing/fast-tracking)")
            recommendations.append("Evaluate additional resource allocation")

        if predicted_delay > 0 and current_progress < 0.5:
            recommendations.append("Review critical path activities for optimization")

        if project_data.get('spi', 1.0) < 0.9:
            recommendations.append("Schedule Performance Index is low - investigate root causes")

        if project_data.get('num_change_orders', 0) > 5:
            recommendations.append("High change order volume - improve change management process")

        if not recommendations:
            recommendations.append("Project on track - maintain current pace")

        return recommendations

    def update_forecast_with_progress(self, project_id: str,
                                       progress_history: List[ProgressSnapshot],
                                       project_data: Dict) -> ScheduleForecast:
        """Update forecast based on current progress trajectory."""

        if len(progress_history) < 2:
            return self.forecast_completion(project_data, 0, datetime.now())

        # Calculate trends
        recent = progress_history[-5:]
        progress_rates = []
        for i in range(1, len(recent)):
            days = (recent[i].date - recent[i-1].date).days
            if days > 0:
                rate = (recent[i].actual_progress - recent[i-1].actual_progress) / days
                progress_rates.append(rate)

        avg_rate = np.mean(progress_rates) if progress_rates else 0
        current_progress = progress_history[-1].actual_progress

        # Estimate remaining duration
        remaining_progress = 100 - current_progress
        if avg_rate > 0:
            remaining_days = remaining_progress / avg_rate
        else:
            remaining_days = 365  # Fallback

        # Adjust with SPI
        current_spi = progress_history[-1].spi
        if current_spi > 0:
            adjusted_remaining = remaining_days / current_spi
        else:
            adjusted_remaining = remaining_days

        # Get base forecast
        base_forecast = self.forecast_completion(
            project_data, current_progress, datetime.now()
        )

        # Blend predictions
        progress_completion = datetime.now() + timedelta(days=int(adjusted_remaining))

        # Weight recent progress more heavily
        blended_completion = base_forecast.predicted_completion + (
            (progress_completion - base_forecast.predicted_completion) * 0.6
        )

        return ScheduleForecast(
            project_id=project_id,
            forecast_date=datetime.now(),
            predicted_completion=blended_completion,
            confidence_interval=base_forecast.confidence_interval,
            delay_probability=base_forecast.delay_probability,
            delay_days=int((blended_completion - pd.to_datetime(project_data['planned_end'])).days),
            key_risk_factors=base_forecast.key_risk_factors + [f"Current SPI: {current_spi:.2f}"],
            recommended_actions=base_forecast.recommended_actions
        )

    def generate_forecast_report(self, forecast: ScheduleForecast, project_name: str) -> str:
        """Generate forecast report."""
        lines = ["# Schedule Forecast Report", ""]
        lines.append(f"**Project:** {project_name}")
        lines.append(f"**Forecast Date:** {forecast.forecast_date.strftime('%Y-%m-%d')}")
        lines.append("")

        lines.append("## Completion Forecast")
        lines.append(f"**Predicted Completion:** {forecast.predicted_completion.strftime('%Y-%m-%d')}")
        lines.append(f"**Confidence Interval:** {forecast.confidence_interval[0].strftime('%Y-%m-%d')} to {forecast.confidence_interval[1].strftime('%Y-%m-%d')}")
        lines.append(f"**Predicted Delay:** {forecast.delay_days} days")
        lines.append(f"**Delay Probability:** {forecast.delay_probability:.1%}")
        lines.append("")

        lines.append("## Risk Factors")
        for risk in forecast.key_risk_factors:
            lines.append(f"- ⚠️ {risk}")
        lines.append("")

        lines.append("## Recommended Actions")
        for action in forecast.recommended_actions:
            lines.append(f"- {action}")

        return "\n".join(lines)

Read the full file on GitHub · 436 lines

Files

What ships with it

2 files beside SKILL.md in the same directory: the scripts, references and assets a skill reads on demand. Not counted in the per-session cost; read them before you install if any of them is executable.

Changes

What this file has done since we first saw it

Hashed on every crawl. A supply-chain change to an agent config is a question of when, not whether, so the history is kept rather than the latest state alone.

  1. 8d ago First seen · 436 lines · 28 tokens per session scan A 4831a1b4f911

Subscribe to this mod's changes

schedule-forecaster is a skill published in the GitHub repository datadrivenconstruction/DDC_Skills_for_AI_Agents_in_Construction (308 stars, last pushed 20d ago), licensed MIT. It adds 28 tokens to every session and 3,501 once invoked, about $0.0001 per session on Opus 5. A static security scan graded it A with 0 findings. No closer match exists in the catalogue, so it is treated as the original; first seen 2026-09-03.

Related

Other skills, from other repositories

plan

Plan features spanning multiple domains: billing (Stripe), auth (RBAC), real-time (Presence), webhooks, jobs (Oban). Use when designing interconnected systems or converting review findings into tasks.

oliver-kriska/claude-elixir-phoenix · 42 tokens

work

Execute Elixir/Phoenix plan tasks with progress tracking. Use after /phx:plan to implement features with mix compile and mix test verification after each step, or --continue to resume interrupted work.

oliver-kriska/claude-elixir-phoenix · 43 tokens

phx-deps-update

Bump outdated Hex deps — inventory, snapshot changelogs, update, fix breaks, split reviewable PRs (patches bundled, majors solo). Use to upgrade/bump Elixir dependencies or when versions fall behind. NOT for deps.get failures (phx-investigate).

oliver-kriska/claude-elixir-phoenix · 62 tokens

proposal-writer

Write a client proposal, quote, scope of work, or engagement letter for a service business. Covers project understanding, scope, timeline, pricing presentation, and terms. Use whenever the user asks for a proposal, quote, project proposal, client proposal, SOW, statement of work, engagement letter, or B2B service…

jezweb/claude-skills · 85 tokens

team-update

Post project updates to team chat, gather feedback, triage responses, and plan next steps. Adapts to available tools (chat, git, issues, tasks). First run discovers tools and saves a playbook; subsequent runs execute from the playbook. Trigger with 'team update', 'post update', 'sync with team', 'standup', 'check team…

jezweb/claude-skills · 94 tokens

daily-working

End-to-end pipeline: pull a task from the project's task tracker by ID (Redmine or GitHub Issues today, more addable via a new adapter), sanity-check and impact-assess it against the codebase before touching anything, implement it with the Claude CLI, verify the result in a real browser via the Claude Chrome extension…

tms-tungnguyen3/daily_working · 98 tokens