Getting it into your agent
One page per mod, every tool's command on it. A separate URL per tool would split the same page into five that compete with each other.
npx skills add jdmorag97-rgb/DDC_Skills_for_AI_Agents_in_Construction --skill critical-path-analyzergit clone --depth 1 https://github.com/jdmorag97-rgb/DDC_Skills_for_AI_Agents_in_ConstructionWrote this? Show the measurements
A badge with what this costs and how it scanned, read live from this page, so it follows the numbers instead of freezing them. Markdown for a README, HTML for a documentation site or a project page.
[](https://agentmods.dev/skills/jdmorag97-rgb/ddc_skills_for_ai_agents_in_construction/critical-path-analyzer)<a href="https://agentmods.dev/skills/jdmorag97-rgb/ddc_skills_for_ai_agents_in_construction/critical-path-analyzer"><img src="https://agentmods.dev/badge/skills/jdmorag97-rgb/ddc_skills_for_ai_agents_in_construction/critical-path-analyzer/github.svg" alt="Measured on agentmods" height="20"></a>Or the 80×15 button, for a site that already has a row of RSS and ATOM ones. Only the verdict fits; the numbers stay here.
<a href="https://agentmods.dev/skills/jdmorag97-rgb/ddc_skills_for_ai_agents_in_construction/critical-path-analyzer"><img src="https://agentmods.dev/badge/skills/jdmorag97-rgb/ddc_skills_for_ai_agents_in_construction/critical-path-analyzer.svg" alt="Reviewed on agentmods" width="80" height="20"></a>What it costs to keep this loaded
Counted locally with the o200k_base tokenizer, which is exact for GPT models; Claude uses its own tokenizer and its counts differ. Treat this as one consistent yardstick across the catalogue rather than a bill. Prices are per million input tokens.
| Model | Per session | Once invoked |
|---|---|---|
| Fable 5.1 | $0.00025 | $0.02554 |
| Opus 5.5 | $0.00010 | $0.01022 |
| Sonnet 5.5 | $0.00005 | $0.00511 |
| Haiku 4.5 | $0.00003 | $0.00255 |
Grade A, and why
critical-path-analyzer scanned grade A with 0 findings against 26 rules in 11 categories — prompt injection, anti-refusal, data exfiltration, privilege escalation, supply chain, agent snooping, system-prompt leakage, SSRF and excessive agency — measured 1mo ago.
A static scan of the body, not an audit. Every finding is printed with the line that produced it so you can judge whether it matters here. A mod is markdown that instructs an agent; that is exactly why what it instructs is worth reading.
Nothing flagged
None of the 26 patterns this scan looks for appear in this file: no shell pipes, no recursive deletes, no credential paths, no hidden text, no instruction-override or anti-refusal phrasing, no agent-config snooping. That is not a guarantee, it is the absence of the things that are checkable.
This is a copy
100% identical to critical-path-analyzer — 0 lines differ, which has more behind it and is treated as the original. This page carries a canonical link to it rather than competing with it.
How it starts
The opening of the file, as written. The whole thing — 376 lines — stays where its author put it; the contents beside it link to each section on GitHub.
Critical Path Analyzer
Business Case
Problem Statement
Schedule management requires understanding:
- Which activities are critical?
- How much float exists?
- What delays impact completion?
- Where to focus resources?
Solution
Analyze schedule network to identify critical path, calculate float, and provide actionable schedule insights.
Technical Implementation
import pandas as pd
import numpy as np
from typing import Dict, Any, List, Optional, Set
from dataclasses import dataclass, field
from datetime import date, timedelta
from enum import Enum
from collections import defaultdict
class ActivityStatus(Enum):
NOT_STARTED = "not_started"
IN_PROGRESS = "in_progress"
COMPLETED = "completed"
DELAYED = "delayed"
@dataclass
class Activity:
activity_id: str
name: str
duration: int # days
predecessors: List[str]
early_start: int = 0
early_finish: int = 0
late_start: int = 0
late_finish: int = 0
total_float: int = 0
free_float: int = 0
is_critical: bool = False
status: ActivityStatus = ActivityStatus.NOT_STARTED
percent_complete: float = 0
actual_start: Optional[date] = None
actual_finish: Optional[date] = None
@dataclass
class CriticalPathResult:
critical_path: List[str]
project_duration: int
activities: Dict[str, Activity]
near_critical: List[str] # Float < 5 days
total_float_days: int
class CriticalPathAnalyzer:
"""Analyze project critical path."""
NEAR_CRITICAL_THRESHOLD = 5 # days
def __init__(self, project_start: date):
self.project_start = project_start
self.activities: Dict[str, Activity] = {}
def add_activity(self,
activity_id: str,
name: str,
duration: int,
predecessors: List[str] = None):
"""Add activity to network."""
self.activities[activity_id] = Activity(
activity_id=activity_id,
name=name,
duration=duration,
predecessors=predecessors or []
)
def import_from_dataframe(self, df: pd.DataFrame):
"""Import activities from DataFrame."""
for _, row in df.iterrows():
preds = row.get('predecessors', '')
if pd.isna(preds):
pred_list = []
else:
pred_list = [p.strip() for p in str(preds).split(',') if p.strip()]
self.add_activity(
activity_id=str(row['activity_id']),
name=row['name'],
duration=int(row['duration']),
predecessors=pred_list
)
def _forward_pass(self):
"""Calculate early start and early finish (forward pass)."""
# Topological sort
sorted_activities = self._topological_sort()
for activity_id in sorted_activities:
activity = self.activities[activity_id]
# Early start = max(early finish of all predecessors)
if not activity.predecessors:
activity.early_start = 0
else:
activity.early_start = max(
self.activities[pred].early_finish
for pred in activity.predecessors
if pred in self.activities
)
activity.early_finish = activity.early_start + activity.duration
def _backward_pass(self):
"""Calculate late start and late finish (backward pass)."""
# Find project duration
project_duration = max(a.early_finish for a in self.activities.values())
# Build successors map
successors = defaultdict(list)
for activity_id, activity in self.activities.items():
for pred in activity.predecessors:
if pred in self.activities:
successors[pred].append(activity_id)
# Reverse topological order
sorted_activities = self._topological_sort()[::-1]
for activity_id in sorted_activities:
activity = self.activities[activity_id]
# Late finish = min(late start of all successors)
if activity_id not in successors or not successors[activity_id]:
activity.late_finish = project_duration
else:
activity.late_finish = min(
self.activities[succ].late_start
for succ in successors[activity_id]
)
activity.late_start = activity.late_finish - activity.duration
# Calculate floats
activity.total_float = activity.late_start - activity.early_start
activity.is_critical = activity.total_float == 0
def _topological_sort(self) -> List[str]:
"""Topological sort of activities."""
visited = set()
result = []
def visit(activity_id: str):
if activity_id in visited:
return
visited.add(activity_id)
activity = self.activities.get(activity_id)
if activity:
for pred in activity.predecessors:
if pred in self.activities:
visit(pred)
result.append(activity_id)
for activity_id in self.activities:
visit(activity_id)
return result
def calculate_critical_path(self) -> CriticalPathResult:
"""Calculate critical path and all float values."""
self._forward_pass()
self._backward_pass()
# Find critical path
critical_activities = [
a.activity_id for a in self.activities.values()
if a.is_critical
]
# Near-critical activities
near_critical = [
a.activity_id for a in self.activities.values()
if 0 < a.total_float <= self.NEAR_CRITICAL_THRESHOLD
]
project_duration = max(a.early_finish for a in self.activities.values())
total_float = sum(a.total_float for a in self.activities.values())
return CriticalPathResult(
critical_path=critical_activities,
project_duration=project_duration,
activities=self.activities,
near_critical=near_critical,
total_float_days=total_float
)
def get_schedule_dates(self) -> pd.DataFrame:
"""Get schedule with dates."""
data = []
for activity in self.activities.values():
early_start_date = self.project_start + timedelta(days=activity.early_start)
early_finish_date = self.project_start + timedelta(days=activity.early_finish)
late_start_date = self.project_start + timedelta(days=activity.late_start)
late_finish_date = self.project_start + timedelta(days=activity.late_finish)
data.append({
'Activity ID': activity.activity_id,
'Name': activity.name,
'Duration': activity.duration,
'Early Start': early_start_date,
'Early Finish': early_finish_date,
'Late Start': late_start_date,
'Late Finish': late_finish_date,
'Total Float': activity.total_float,
'Critical': 'Yes' if activity.is_critical else 'No'
})
return pd.DataFrame(data)
def analyze_delay_impact(self,
activity_id: str,
delay_days: int) -> Dict[str, Any]:
"""Analyze impact of delay on project."""
activity = self.activities.get(activity_id)
if not activity:
return {}
absorbed_by_float = min(delay_days, activity.total_float)
project_delay = max(0, delay_days - activity.total_float)
# Find affected activities
affected = []
if project_delay > 0:
# Activities that could be affected (successors)
for a in self.activities.values():
if activity_id in a.predecessors:
affected.append(a.activity_id)
return {
'activity': activity_id,
'delay_days': delay_days,
'available_float': activity.total_float,
'absorbed_by_float': absorbed_by_float,
'project_delay': project_delay,
'affected_activities': affected,
'is_critical_delay': project_delay > 0
}
def suggest_acceleration(self,
target_reduction: int) -> List[Dict[str, Any]]:
"""Suggest activities to accelerate to meet target."""
result = self.calculate_critical_path()
suggestions = []
# Focus on critical activities
for activity_id in result.critical_path:
activity = self.activities[activity_id]
# Assume can reduce by 20% max
max_reduction = int(activity.duration * 0.2)
if max_reduction > 0:
suggestions.append({
'activity': activity_id,
'name': activity.name,
'current_duration': activity.duration,
'max_reduction': max_reduction,
'reason': 'Critical path activity'
})
# Sort by potential impact
return sorted(suggestions, key=lambda x: x['max_reduction'], reverse=True)
def export_analysis(self, output_path: str) -> str:
"""Export analysis to Excel."""
result = self.calculate_critical_path()
with pd.ExcelWriter(output_path, engine='openpyxl') as writer:
# Summary
summary_df = pd.DataFrame([{
'Project Start': self.project_start,
'Project Duration': result.project_duration,
'Project Finish': self.project_start + timedelta(days=result.project_duration),
'Critical Activities': len(result.critical_path),
'Near-Critical Activities': len(result.near_critical),
'Total Float (days)': result.total_float_days
}])
summary_df.to_excel(writer, sheet_name='Summary', index=False)
# Schedule
schedule_df = self.get_schedule_dates()
schedule_df.to_excel(writer, sheet_name='Schedule', index=False)
# Critical Path
critical_df = pd.DataFrame([
{
'Activity': a_id,
'Name': self.activities[a_id].name,
'Duration': self.activities[a_id].duration
}
for a_id in result.critical_path
])
critical_df.to_excel(writer, sheet_name='Critical Path', index=False)
return output_path
What ships with it
2 files beside SKILL.md in the same directory: the scripts, references and assets a skill reads on demand. Not counted in the per-session cost; read them before you install if any of them is executable.
What this file has done since we first saw it
Hashed on every crawl. A supply-chain change to an agent config is a question of when, not whether, so the history is kept rather than the latest state alone.
- 1mo ago First seen · 376 lines · 25 tokens per session scan A 1262c5690310
critical-path-analyzer is a skill published in the GitHub repository jdmorag97-rgb/DDC_Skills_for_AI_Agents_in_Construction (2 stars, last pushed 8mo ago), licensed MIT. It adds 25 tokens to every session and 2,554 once invoked, about $0.0001 per session on Opus 5.5. A static security scan graded it A with 0 findings. It is 100% identical to critical-path-analyzer, differing in 0 lines, and is treated as a copy.
Other skills, from other repositories
story-readiness
Checks whether a story is ready to implement: clear acceptance criteria, no open questions, valid ADR and dependencies. Use when the user asks if a story, or the sprint's stories, are ready to start or build.
recipe-create-meet-space
Create a Google Meet meeting space and share the join link.
workthreads
SpecStory Workthreads - a weekly work-thread rollup across a team's repos from SpecStory coding histories (any agent - Claude Code, Codex, Cursor, Gemini, and more). It groups the window's sessions into threads of work per project and labels each new / open / recently closed, so a lead sees what shipped, what is still…
atmos-config
Atmos root configuration: atmos.yaml discovery, precedence, deep merging, basepath, imports, minimal bootstrap, and routing to narrower Atmos skills.
qa-project-bootstrap
Onboard a new QA engineer to an existing codebase, or audit an existing test architecture. Produces a 30-day ramp plan: codebase orientation, framework walkthrough, test architecture audit, mentorship pairing, and first-test guidance. Use when: "QA onboarding," "new tester," "ramp up," "test architecture audit,"…
remove
Remove a deployed framework or addon from the current workspace.